| OBSERVATIONS AND CORRECTIVE ACTIONS |
| Item No.
Violations cited in this report must be corrected within the time frames below.
|
| 4: R: Employee beverage stored on prep table in back of kitchen. Remove |
| 20: Liquid eggs stored above grill at room temperature not maintained within proper cold holding temp. MCHD temped at 69F. Facility voluntarily |
| discarded. COS |
| 20: Coffee creamer cooler at front service area turned off during inspection. MCHD temped creamer in cooler at 75F. Facility voluntarily |
| discarded. COS. Facility noted the breaker tripped for the cooler and reset the breaker. By the end of inspection, the cooler was maintaining |
| a temp of 36F. |
| 34: Readily visible thermometers lacking in chest freezer near fry line and in smoothie machine. Provide. |
| 37: R: Hair restraint lacking for manager handling/prepping food orders at front service counter. |
| 37: Employee jackets stored on top of wrapped sandwich buns. COS |
| 46: Cold faucet handle on right side faucet assembly at 3 bay sink inoperable. Left side assembly can fill 3 bay sink for warewashing. |
| Repair immediately. MCHD shall follow-up in 24 hours to ensure repair to 3 bay sink faucet assembly. |
| 47: Food-like debris build-up under grills, fryers and equipment at drive thru window. Clean and sanitize. |
| 47: Food-like debris on inside of microwave near 2 door reach-in cooler. |
| 49: Cold line faucet handle at mop sink missing, leak present at mop sink handle. Repair immediately. MCHD shall follow-up to ensure repair |
| 52: Dumpster lids open. Keep dumpster lids closed. |
| 53: 3R: Floor tiles chipped and damaged in the basement storage area. Repair/replace. |
| 53: Visible air gap at bottom of basement door. Repair to ensure tight seal. |
| Note: Correct and maintain compliance. Additional repeats may lead to further action in accordance to law. |
| Manager stated building has been approved by local township board for demolition. Target demolition date is June 2013. |
| Ensure facility contacts MCHD for Plan Review prior to reconstructing future building. |
| A plan review packet can be downloaded at www.health.montcopa.org |
| A plan review packet can be downloaded at www.health.montcopa.org |